Pit Lane Rehabilitation at Circuit Gilles-Villeneuve
For the Société du parc Jean-Drapeau, Charex rebuilt the pit lane of the Circuit Gilles-Villeneuve from October 2021 to May 2022.
The site development and sewer work included demolishing the old surfaces, installing the infrastructure, and paving the new pit lane.
Scope of work
- Demolition of existing surfaces
- Sewer work
- New pit lane pavement
- Site development
Project gallery
Click a photo to enlarge it.
The project on video
Project details
- CategoryCivil engineering
- ClientSociété du parc Jean-Drapeau
- LocationMontréal – Parc Jean-Drapeau
- Start of workOctober 2021
- End of workMay 2022
- Contract value$2,434,857 (before taxes)